    Hot off the press, the NH SEC has delayed a decision on Northern Pass six months until March 2018 (it was Sept 2017). https://www.usnews.com/news/best-sta...ision-deadline

    This is pretty significant as the Mass renewable RFP suppliers will most likely be locked in by then. NPs fate is not directly tied to it but would be a major boost.

    It will be interesting to see the spin from both sides. I also will be interested on the recently announced Balsams start of construction by this fall.
    Last edited by peakbagger; 08-31-2017 at 06:19 PM.

  2. #512
    Senior Member skiguy's Avatar
    Join Date
    Dec 2004
    Posts
    2,074
    "I'm getting up and going to work everyday and I am stoked. That does not suck!"__Shane McConkey

  3. #513
    Senior Member skiguy's Avatar
    Join Date
    Dec 2004
    Posts
    2,074
    "I'm getting up and going to work everyday and I am stoked. That does not suck!"__Shane McConkey

  4. #514
    Senior Member dug's Avatar
    Join Date
    Sep 2003
    Location
    Xanadu
    Posts
    1,865
    http://www.unionleader.com/energy/Fo...tains-09072017

    U.S. Forest Service recommends permit to bury Northern Pass lines in White Mountains

  5. #515
    Senior Member
    Join Date
    Sep 2003
    Location
    Gorham NH
    Posts
    4,919
    http://indepthnh.org/2017/09/28/epa-...-for-wetlands/

    Interesting, the EPA had signed off on the project but is recommending more burial in the north country. The NH DES had similar comments previously and would not sign off on the project but since the new governor put in his hand picked DES director, that objection seems to have gone away.

    This would make a big difference on the impact to northern NH and I expect many objections to the project would be dropped by local towns and residents. There is a new batch of folks objecting as the details on the burial project come out.

    I guess it comes down to how confident NP is on if they have the votes on the SEC. I would expect they have spent a lot of time figuring out how each SEC member is going to vote, recent PR is they are rush to get it over which implies that they think they have the votes but the SEC has delayed the project votes until 2018 which implies they don't have full control of the board.

  6. #516
    Senior Member
    Join Date
    Sep 2003
    Location
    Gorham NH
    Posts
    4,919
    Hydro Quebec has been doing a lot of behind the scenes lobbying with Mass and CT politicians to develop a market for the power from NP. Mass has a rule in place for many years that excluded hydro power produced by projects like NP as counting towards the Mass Renewable Power goals. This type of hydro is generally regarded as "brown" hydro in that some political body has decided that the environmental and social impacts of project exceed the environmental benefits. This decision made years ago is definitely a big impact on the Mass power market as the cost of HQ hydro power is far less then other renewables like wind and solar. It is also available 24/7 unlike wind and solar. Mass is currently going out for a request for proposals for a large block of renewable power and anyone being awarded this contract get a guaranteed long term contract for power and the ability to have the ratepayers fund the construction. There have been numerous bidders from all over the region https://macleanenergy.com/83d/83d-bids/.

    This is not the only game in town but its a big one and NP is definitely very interested in getting the contract. Unfortunately for them the timing doesn't seem to be lining up as the NH state decision if the project can be built after the Mass RFP second cut is made http://www.unionleader.com/article/2...89/1028/NEWS05.

    NP has also been cut out of at least one other renewable power RFP. Its not the end as the parent company of NP has a lot of political influence and most likely could push some other state to another renewable buy. This was probably a good bet until the administration announced that they are scuttling the EPA Clean Power Plan regulations and encouraging coal powered plants to remain in business longer which will most likely put a pause in any renewable efforts in the region as it will just make the New England region even more economically disadvantaged compared to other regions of the country burning high carbon fuels.

    Northern Utilities CEO and management has bet their prestige and most likely jobs on NP getting built, if they don't get in on the Mass RFP the likelihood of NP getting built could really slam their financials.

  7. #517
    Senior Member
    Join Date
    Sep 2003
    Location
    Gorham NH
    Posts
    4,919
    All sorts of news coming out almost daily but the real news is the schedule of the public deliberation by the SEC

    http://www.unionleader.com/energy/No...tions-11222017

    Stock up on popcorn as these sessions and the associated discussions will seal the fate of the project one way or another. If, as some speculate, NP has already figured they have the votes through political ties (and a heaping helping of contributions over the years) the sessions will go one way while if its still in doubt, the approach will head in an entirely opposite direction. I doubt the sessions will get curtailed by the determination that one aspect of the project makes it approvable

  8. #518
    Senior Member
    Join Date
    Sep 2003
    Location
    Gorham NH
    Posts
    4,919
    CMP in Maine touting a lower cost alternative. They actually went out and bought additional right of way for the new line to where it would hook up to the HQ grid

    http://www.pressherald.com/2017/12/0...through-maine/

  9. #519
    Member Hammerdee's Avatar
    Join Date
    Sep 2003
    Location
    Epping, NH
    Posts
    30
    Looks like one Vermont project may be in trouble; it was aimed more at transmitting NY wind power than hydro:

    https://vtdigger.org/2017/12/10/deve...ake-champlain/

  10. #520
    Senior Member Raven's Avatar
    Join Date
    Jan 2010
    Location
    NH Seacoast
    Posts
    1,546
    Ashland pushing back. Voters have said twice they do NOT want NP.

    http://www.laconiadailysun.com/newsx...-northern-pass
    Humankind has not woven the web of life.
    We are but one thread within it.
    Whatever we do to the web, we do to ourselves.
    All things are bound together.
    All things connect.
    ~ Chief Seattle, 1854 ~

  11. #521
    Moderator bikehikeskifish's Avatar
    Join Date
    Oct 2006
    Location
    New Hampshire
    Posts
    5,304
    Bike, Hike, Ski, Sleep. Eat, Fish, Repeat.

  12. #522
    Senior Member
    Join Date
    Sep 2003
    Location
    Gorham NH
    Posts
    4,919
    They have been promising local excavation and trucking contractors for years that when it gets approved, they will be given as much work as they can handle. The local I got this from was planning to retire after the project and was sitting on a yard full of equipment paying loans for work that didn't come for a couple of construction seasons. He still plans to support it if he can find folks to drive for him. There is a major shortage of labor in the area and not lot of accommodations, it will definitely be a boom town if it goes. I expect the Balsams is going to regret linking with NP approval as they will have a tough time getting labor as NP will be paying a lot more. It happened when PNGTS went in, a lot of locals made a couple of years of pay during construction and it was gone within a few months of the end of the project. There was a wave of divorces about that time.

    The actual skilled work is all specialized out of state union contractors. IBEW has a token training program so they can staff locals as apprentices.

  13. #523
    Senior Member Raven's Avatar
    Join Date
    Jan 2010
    Location
    NH Seacoast
    Posts
    1,546
    Quote Originally Posted by peakbagger View Post
    The actual skilled work is all specialized out of state union contractors. IBEW has a token training program so they can staff locals as apprentices.
    Unfortunately this fact is not really advertised when jobs are promised. They don't tell you they already have the skilled labor lined up.
    Humankind has not woven the web of life.
    We are but one thread within it.
    Whatever we do to the web, we do to ourselves.
    All things are bound together.
    All things connect.
    ~ Chief Seattle, 1854 ~

  14. #524
    Senior Member
    Join Date
    Sep 2003
    Location
    Gorham NH
    Posts
    4,919
    This is far more a PR effort to hopefully push some members of the SEC to vote their way then a real effort to staff the project. They decided early on to use union labor on the skilled work. Last thing I knew there was only one IBEW local in NH and it had limited members. HVDC work is specialized and buried even more so. That works is already locked in with an out of state national firm. Cianbro in Maine is non union and does do it but expect the Eversource would have a riot from their unions if Cianbro was allowed to bid. I would speculate that the proposed CMP line in Maine would be a Cianbro project as they did a major line upgrade through Maine a few years ago. Eversource did do a carve out for site work and excavation for NP and that's going to suck up every laborer trucker and equipment operator in the region, it keeps the local politicians who sold their souls in office.

    There could be some environmental jobs acting as site inspector to try to prevent the project from doing more damage than necessary.

  15. #525
    Senior Member
    Join Date
    Sep 2003
    Location
    Gorham NH
    Posts
    4,919
    http://indepthnh.org/2017/12/14/nort...e-of-the-line/

    Interesting that HQ is planning on burying 12 miles of NP on the Canadian side of the border. More interesting is the cost per mile which is much lower than NP had claimed. As far as I know, no party has really done any preliminary boring along any possible road alignments to establish underground conditions in Coos county so it comes down to whose opinion not based on facts should be used to justify a long term scar on the land in northern NH.